GYPSUM PLASTER – INSPECTION & TEST PLAN Gypsum plaster is highly recommended by Architects due to its many advantages as an alternative...
Currently Working in Tata projects as Engineer Construction, Dam Projects, Banda Irrigation Projects
Currently Working in Tata projects Ltd, Composite Gravity Dam Projects , Heavy structure Construction, irrigation pipe line, BPT (Break pressure Tank), Construction Execution, Etc.. And in previous company NCC Limited - water supply projects , WTP, ESR , Pipe Line , Over Head Tank , Rising Main , Distribution pipe line ,HDPE , DI, GI, House Connection, Water Sector, Water Treatment Plant, Irrigation, Water Supply, BBS , Structure of Clear Water Reservior( CWR) , Cascade Airator, CLF , Filter House , Staff Room , Admin Block ,Etc.
Layout Marking, Level check, excavation, foundation, Spillway, Radial Gate, Up stream training wall , Down Stream Training wall, Gallery, Sump Well, instruments, stilling basin, Consolidation Grouting, Curtain Grouting, Percolation test, Logue on Vallue, Measurement, execution and quality control, Etc.
BPT ( Break Pressure Tank) Pump House, MS pipe Gunniting,MS pipe Laying, DI pipe Laying , HDPE Pipe Laying, Hydrotest etc.
Innovative, Risk Management, Cost Control, Progress, local issues Management, team lead, DPR, Planning, execution, quality control etc..
Intake Well, Casecade airator, CLF, F Mixer, Filter Bed, Filter House, Chlorination House, CWR, Pump House, etc..
OHT (Over Head Tank) CWR ( Clear Water Reservoir), ESR ( Elevated Storage Reservoir) , DI pipe line , GI pipe line , HDPE pipe line , Jointing and laying , Hydrotest, commissioning, etc.. .
Turn Key Basis (OHT, Pump House, Rising Main, Tube well, Pipe Distribution System, Staff Quarter and Boundary Wall related works)
Turn Key Basis OHT, Pump House, Rising Main, Tube well, Pipe Distribution System, Staff Quarter and Boundary Wall related works ( 63mm, 75mm, 90mm, 110mm , 140mm, 160mm, 180mm, 200mm HDPE, And DI 250, 300, 350 mm) Hydrotest Commissioning etc.
Turn Key Basis OHT, Pump House, Rising Main, Tube well, Pipe Distribution System, Staff Quarter and Boundary Wall related works ( 63mm, 75mm, 90mm, 110mm , 140mm, 160mm, 180mm, 200mm HDPE, And DI 250, 300, 350 mm) Hydrotest Commissioning etc.
Turn Key Basis OHT, Pump House, Rising Main, Tube well, Pipe Distribution System, Staff Quarter and Boundary Wall related works ( 63mm, 75mm, 90mm, 110mm , 140mm, 160mm, 180mm, 200mm HDPE, And DI 250, 300, 350 mm) Hydrotest Commissioning etc.
Turn Key Basis OHT, Pump House, Rising Main, Tube well, Pipe Distribution System, Staff Quarter and Boundary Wall related works ( 63mm, 75mm, 90mm, 110mm , 140mm, 160mm, 180mm, 200mm HDPE, And DI 250, 300, 350 mm) Hydrotest Commissioning etc.
Turn Key Basis OHT, Pump House, Rising Main, Tube well, Pipe Distribution System, Staff Quarter and Boundary Wall related works ( 63mm, 75mm, 90mm, 110mm , 140mm, 160mm, 180mm, 200mm HDPE, And DI 250, 300, 350 mm) Hydrotest Commissioning etc.
Turn Key Basis OHT, Pump House, Rising Main, Tube well, Pipe Distribution System, Staff Quarter and Boundary Wall related works ( 63mm, 75mm, 90mm, 110mm , 140mm, 160mm, 180mm, 200mm HDPE, And DI 250, 300, 350 mm) Hydrotest Commissioning etc.
Turn Key Basis OHT, Pump House, Rising Main, Tube well, Pipe Distribution System, Staff Quarter and Boundary Wall related works ( 63mm, 75mm, 90mm, 110mm , 140mm, 160mm, 180mm, 200mm HDPE, And DI 250, 300, 350 mm) Hydrotest Commissioning etc.
First of all I love music, country music is my favorite. Love watching movies and playing games with my buddies. I spend quite a lot of time in traveling and photography, these keeps me fresh for working environment. I also spend time researching some knowledge.
HDPE PIPE SPECIFICATION NOTES By Er. Banwari Lal (contact@erbanwarilal.com) · The maximum allowable hydrostatic design st...
Regarding any civil engineering problem and for hiring expert employee staff contact me